This website uses cookies primarily for visitor analytics. Certain pages will ask you to fill in contact details to receive additional information. On these pages you have the option of having the site log your details for future visits. Indicating you want the site to remember your details will place a cookie on your device. To view our full cookie policy, please click here. You can also view it at any time by going to our Contact Us page.

NAO criticises HMRC estates PFI deal

10 December 2009

An NAO report published last week into the HM Revenue & Customs PFI deal with Mapeley says it has not achieved value for money, it had no long-term plan and had not obtained all available savings; now the economic downturn puts the deal at risk.

HRMC Whitehall, London

By transferring ownership or leases of around 60 per cent of its estate (591 properties) to a private contractor, Mapeley, in 2001, the Inland Revenue and HM Customs & Excise planned to reduce their running costs and had the opportunity to save up to £1.2bn by reducing the size of the estate.  The contract allowed for a smooth estates merger, following the merger of the two departments in 2005  which became HM Revenue and Customs. The Departments signed the contract with Mapeley STEPS Contractor Limited, and transferred the properties and leases to Mapeley STEPS Limited. Both companies are part of the Mapeley Group.
HMRC has the flexibility to vacate up to 60 per cent of its estate over the 20 year contract, allowing it to save up to £1.2 bn. But it has not recognised the contract as a major strategic asset nor committed appropriate commercial skills to managing it. As a result, the total possible savings available now amount to £900m. To date, the contract has cost £312m more than originally forecast, as a result of fewer instances than forecast of vacating buildings, unrecoverable VAT payments, and changes in requirements.
To achieve savings on its estate, HMRC is now planning to vacate a significant number of its buildings by 2011. This vacations programme creates areas of specific financial pressure for Mapeley, exacerbated by the economic downturn and falling property values. HMRC does not yet have an agreed way forward with Mapeley.  If Mapeley were to default on the contract, HMRC could incur significant one-off and ongoing costs.
The NAO’s 2004 report found that the Department secured a competitive price from Mapeley but warned that good risk management would be essential on the 20 year deal signed in 2001. However HMRC has generally reacted to risks and issues as they arise rather than strategically managing the contract. It lacks full visibility of all the gains and losses that Mapeley has obtained from the contract, which would be critical to inform any negotiations.
There is now a significant risk that HMRC will not achieve value for money over the rest of the contract unless it strengthens its management of the contract. There needs to be active management at Board level and HMRC needs to develop an estates strategy. HMRC should monitor overall value for money and form an effective partnership with Mapeley.
Mr Amyas Morse, head of the National Audit Office, said today: “This major contract has been significantly affected, for the contractor Mapeley in particular, by the current economic climate. Mapeley benefited when the property market was expanding but the economic downturn has made the contract more onerous. HMRC must take a significantly more astute commercial approach if it is to deliver value for money for the taxpayer.”


Contact Details and Archive...

Print this page | E-mail this page

http://www.fsifm.com
PFM


MOST VIEWED...

View more articles
Article image

Why the Law Says You Need a Nappy Bin Disposal Service

At home, parents are used to disposing of their babies’ used nappies the same way they do any other domestic waste - bagging it up and sticking it in the r...

Benchmarking maintenance

BSRIA has just published this year's operation and maintenance benchmarking report as a guide for building operators to evaluate their performance against ...
Article image

Online applications invited for the PFM-hosted visit to ISE 2020

Those wishing to join the annual hosted visit to the internationally-renowned Integrated Services Exhibition exhibition in February can now register their ...
Article image

CSA Conference Secures Additional Industry Support

Scheduled for Tuesday 31st March at The Crystal in London, the first ‘Making Buildings Work’ conference has won the backing from two of the leading names i...
Article image

Prevention better than cure where compliancy and PPM is concerned

Industry experts give their response to the question of whether compliance with legislation should be a focus of maintenance procedures....
Article image

Court action against MoJ after "unfair" contract award

According to The Times, the Ministry of Justice (MoJ) is being sued by Mitie, following claims that it lost out on...